concept feasibility team in category agile

appears as: feasibility team, The feasibility team, feasibility team
Becoming Agile ...in an imperfect world

This is an excerpt from Manning's book Becoming Agile ...in an imperfect world.

Table 8.4. Acme outlines a Feasibility phase for its new process. The new feasibility process accelerates evaluation and gets work started more quickly on urgent projects.

Step

Feasibility phase

Group(s)

Change notes

1 Submit idea to request site. Any employee In the past, ideas were only submitted by Marketing, Sales, or Product Management. Ideas don’t need detailed requirements to be submitted now. The new online form requires minimal population of fields to be accepted.
2 Review queue, and assign features for investigation. Product manager, line managers, or executive team Ideas can be approved for more detailed investigation (feasibility) by managers at any time. Managers decide if a team is needed to help with the research.
3 Research ideas for feasibility. Requestor, or feasibility team In the past, we only used the requestor’s information to determine if an idea was feasible. The team uses the Feasibility Discussion Guide to lead investigative work. (This guide is covered in chapter 10.) The team returns with information such as customer thoughts, information about what the competition is doing, cost/benefit analysis, key risks, time estimates, and main benefits to the customer. The feasibility team creates an elevator statement (covered in chapter 10).
4 Review findings to see if the idea should continue to the Planning phase. Product manager, line managers, or executive team Managers can send an idea on to planning. This is possible because 50% of the team’s capacity is now reserved for unscheduled projects. The other 50% of the capacity is reserved to support projects that come out of the quarterly planning process. A manager can escalate the decision to the executive team if funds are needed or if the project will exceed the remaining capacity in the quarter.
5 Decide to approve, cancel, or defer the idea/project. Product manager, line managers, or executive team Make the call about whether to continue and assemble a project team.
6 Assign resources to the planning team. Product manager, line managers, or executive team We want the planning team to stay with the project throughout development.

First, you must determine what type of team members are needed to do the feasibility work. Second, you need to review the known requirements with the feasibility team and have the members perform research in their respective areas. The feasibility guide (discussed in section 10.3.1) focuses the team on the areas they should be researching during the phase.