Agile Metrics in Action: How to measure and improve team performance

This is an excerpt from Manning's book Agile Metrics in Action: How to measure and improve team performance.

Let’s look at a team which is using Scrum and can’t seem to maintain a consistent velocity. Their Scrum master is keeping track of their accomplishments sprint after sprint and graphing it; as shown in figure 1.14, it’s not looking good.

Figure 1.14. Team 1’s complete story points over time

After showing that to leadership, everyone agrees that the team needs to be more consistent. But what’s causing the problem? The development team decides to pull data from all the developers across all projects to see if there’s someone in particular who needs help with their work. Lo and behold, they find that Joe Developer, a member of Team 1, is off the charts during some of the dips, as shown in figure 1.15. After digging a bit deeper, it is determined that Joe Developer has specific knowledge of the product a different team was working on and was actually contributing to multiple teams during that time. He was overworked, yet it looked as if the team were underperforming.

Figure 1.15. Joe Developer’s contribution is off the charts, but his team is not performing well.

In this case it’s pretty easy to show that the commitment to multiple projects hurts the individual teams, and apparently Joe Developer is way more productive when working on the other team’s product. People are usually eager to show trends like this, especially when they indicate that individual performance is great but for some reason forces outside the team are hurting overall productivity. If you’re being measured, then you might as well ensure that the entire story is being told. In this case the data ended up pointing to a problem that the team could take action on: fully dedicate Joe Developer to one team to help avoid missing goals on another team and to not burn your engineers as you’re delivering product.

  • APM gives you insight into how well your application is built, and BI tells you how your consumers use it:
    • Server health statistics show you how well your application is performing.
    • Arbitrary stats and semantic logging give you measureable stats on how your application is being used.
    • Teams using a DevOps model are more likely to have access to APM data.
  • The delivery team took a look at the BI report and realized that there was no direct link between the work they were doing and the metrics being used to determine if features were successful. Because they were delivering features, the team needed to figure out how those features improved conversion and stickiness on their site. The delivery team decided to start by bringing the BI team into their sprint planning to help them close the gap.

    The team was already using ELK for their logging, so they simply added strongly typed messages to their logs for the events they wanted to track. These started showing up in their dashboard, as shown in figure 6.11.

    Figure 6.11. The Kibana dashboard the team generated to track their statistics

    Now the team was completing the picture. They could see how they were developing, what they were developing, and how it affected their consumers when they deployed changes to the consumer. Now they could use that data to shape what features they should work on next and how they could tweak their development process to ensure they were delivering things the right way.

    Becoming Agile ...in an imperfect world

    This is an excerpt from Manning's book Becoming Agile ...in an imperfect world.

  • Agile processes promote sustainable development. The sponsors, developers, and users should be able to maintain a constant pace indefinitely. In traditional development, the team often has to work late toward the end of a project, although at the beginning of the project they may have taken 2-hour lunch breaks. This is primarily due to the way project activities are distributed across the project’s lifecycle. There isn’t much for developers to do at the beginning of the project, but at the end everything is put on their shoulders because of tight delivery schedules. With agile development, you deliver every two weeks or so, and development begins with the first iteration. Efforts are distributed more consistently throughout the project lifecycle, which leads to a constant development pace for the team.
  • This would be a great time for us to tout how agile came in and saved the day, but that would be a lie. Greg did help his friend prioritize his work and make the deadline, and they did follow some agile principles along the way, but they didn’t put an agile team or process in place. Why? Because it takes time to establish an agile methodology. Teams need time to feel comfortable with agile processes, and they need time to learn how to interact with each other. Managers need time to learn how to lead in an agile environment. The team needs to use an agile process for several months, and then major benefits will begin to become apparent.

    Figure 7.2. An agile leader brings their soft skills together to shepherd the team versus directing them.
  • Buy-in —This phase occurs when you roll out the change and begin implementing it. You created awareness earlier, and you’re looking for the team to consider the change and to use it with your guidance.
  • Ownership —The team has tried the change, begun to believe in it, and adopted it as a standard practice. They don’t need management to encourage them to use it. They believe in it and will use it without being prodded.