Project crashing shortens a project by reducing the duration of one or more critical-path activities, usually through overtime or added resources. Because schedule, cost, and scope are interconnected, acceleration is worthwhile only when earlier completion justifies the additional expense. section 13.5 section 13.6
Use the cost-effective crashing procedure:
- Replace expected activity times with most-likely times and recalculate the critical path when the estimates differ. section 13.5
- Calculate each activity’s weekly crash cost, using the additional cost per unit of time saved and assuming linear crash costs. section 13.5
- Select critical-path activities with the lowest weekly crash costs; crashing noncritical activities raises cost without shortening the overall project. section 13.5
Automated reporting tool project
The activity estimates classify A, B, C, D, E, G, J, K, and L as critical. Activities A, B, C, E, G, K, and L each have a $1,000 weekly crash cost, while noncritical activities such as F, H, and I should not be crashed merely to reduce duration. section 13.5
Table 13.5 Most likely and crash estimates for the automated reporting tool project in weeks and dollars. The most effective way of accelerating a project timeline is to crash one or more critical path activities with the lowest weekly crash costs.
|
Activity
|
Time (weeks)
|
Cost ($)
|
Weekly crash cost ($)
|
Critical path?
|
||
|---|---|---|---|---|---|---|
|
Most likely
|
Crash
|
Most likely
|
Crash
|
|||
|
A
|
3
|
2
|
5,000
|
6,000
|
1,000
|
Yes
|
|
B
|
2
|
1
|
4,000
|
5,000
|
1,000
|
Yes
|
|
C
|
3
|
2
|
5,000
|
6,000
|
1,000
|
Yes
|
|
D
|
5
|
4
|
9,000
|
11,000
|
2,000
|
Yes
|
|
E
|
3
|
2
|
5,000
|
6,000
|
1,000
|
Yes
|
|
F
|
4
|
3
|
8,000
|
9,000
|
1,000
|
No
|
|
G
|
4
|
2
|
8,000
|
10,000
|
1,000
|
Yes
|
|
H
|
3
|
2
|
5,000
|
7,000
|
2,000
|
No
|
|
I
|
3
|
2
|
5,000
|
6,000
|
1,000
|
No
|
|
J
|
4
|
2
|
7,000
|
10,000
|
1,500
|
Yes
|
|
K
|
3
|
1
|
5,000
|
7,000
|
1,000
|
Yes
|
|
L
|
2
|
1
|
4,000
|
5,000
|
1,000
|
Yes
|
Compare most-likely and crash durations, costs, weekly crash costs, and critical-path status for each project activity. section 13.5