A Snowflake task is a user-defined object that runs a SQL statement, stored procedure, or Snowflake Scripting block. It can start at a specified time, recur at an interval, or run after a predecessor finishes. Tasks provide native scheduling and execution for data-pipeline orchestration. section 13.1
Use a task to automate pipeline steps that would otherwise be run manually, such as loading staged files, merging data, and producing reporting summaries. A task needs compute: either a chosen virtual warehouse or Snowflake-managed serverless compute. section 2.5 section 13.1
Scheduled order-processing task
A PROCESS_ORDERS task runs every 10 minutes during testing. Its Snowflake Scripting block truncates a staging table, loads files with COPY INTO, merges orders into a target table, and refreshes a summary table. After validation, suspend it, change the schedule to 11 p.m. UTC, then resume it; new tasks begin suspended. section 2.5
use database BAKERY_DB; use schema ORDERS; create task PROCESS_ORDERS warehouse = BAKERY_WH schedule = '10 M' as begin truncate table ORDERS_STG; copy into ORDERS_STG... #1 merge into CUSTOMER_ORDERS... #2 truncate table SUMMARY_ORDERS; insert into SUMMARY_ORDERS... #3 end;
This task definition shows a warehouse-backed schedule and a single scripting block that groups sequential pipeline SQL operations. section 2.5
For production task orchestration:
- Store tasks and related logging, error-handling, and configuration objects in a dedicated orchestration schema, separate from pipeline data-layer schemas. section 13.1.1
- Model dependent steps as a task graph (DAG): schedule the root task, and let child tasks run after predecessors complete successfully. Streams can supply incremental-processing conditions. section 13.1 section 13.6
- Grant EXECUTE TASK to the role that creates and runs tasks, then test tasks manually before relying on a schedule. section 13.1.2 section 13.6
- Inspect TASK_HISTORY() for execution state, timing, errors, and the next scheduled run. For failures, validate task-body SQL, status, dependencies, predecessors, schedule, and available stream data. section 13.5 section 2.5
- Use logging and a finalizer task to summarize completed task work and send pipeline-completion email notifications when needed. section 13.4.2
Scheduled tasks do not overlap: if a prior scheduled run is still executing when the next time arrives, the later run is skipped. A stream-conditioned task can also be skipped when no data is available. section 13.6