CPU time

As explained in Build High Value Software Systems

The time spent actively progressing a change through activities such as coding, testing, fixing, and reviewing.

A change can take days to deliver while receiving only hours of active work. CPU time here means activity time, also called touch time: the time spent directly progressing a work item. It includes coding, writing or running tests, debugging, addressing review comments, reviewing, merging, and deploying. It does not mean machine CPU usage. section 5.4.2 section 9.2.3

Exclude time when the change is merely waiting: a review queue, a CI result or rerun, a deploy window, or an idle handoff. Count an automated step when it directly transforms the work, but do not count an entire pipeline run as active time if most of it is blocked or queued. This distinction matters because lead time and cycle time show how long delivery took; activity time helps reveal how much of that duration involved progress. section 5.4.2 section 9.2.3

Table 5.2 Activity ratio analysis of a simple workflow
Stage
Activity time
Waiting time
Cycle time
Activity ratio
Implement change
30
0
30
1.00
Run local tests
1
0
1
1.00
CI pipeline (1st run)
1
7
8
0.13
CI rerun (2nd run)
1
7
8
0.13
Code review
6
234
240
0.03
Merge
1
0
1
1.00
Totals
40
248
288
0.14

The workflow totals 40 units of activity time across 288 units of cycle time, for an activity ratio of 0.14. Review accounts for 6 active units but 234 waiting units. Making coding faster would not remove that delay. section 5.4.2

A review queue, before and after

Suppose review takes three hours of active work but the change spends four days at the review station. Dedicated review windows reduce that station’s elapsed time to 1.5 days while active review remains three hours. The improvement comes from a shorter queue, not harder work. section 9.2.3

To use the metric on a real change:

  • Select a recent completed change. Reconstruct its path from first edit to merge, estimating time spent coding, testing, fixing, and reviewing separately from waiting. section 5.8
  • Compare activity time with elapsed time. Activity time divided by cycle time gives a within-work activity ratio; an exercise measuring against the full request-to-delivery lead time instead includes earlier backlog waiting. State which denominator you use. section 5.4.2 section 9.5
  • Find the longest delay, change one cause—such as a flaky test or slow CI stage—and measure the next change. A low ratio points toward waiting; it does not, by itself, identify the bottleneck. section 5.8 section 6.4

How Build High Value Software Systems covers it

How deep it goes
Defines what counts, distinguishes queues from active steps, and works through ratios and before-and-after station measurements.
Examples
Uses a 288-unit workflow with 40 active units and a review station whose elapsed time falls while active work stays constant.
What it assumes
Assumes familiarity with commits, reviews, CI, and issue trackers while defining the flow metrics needed for comparison.
What you can do after
Practice measuring active time on completed changes, locating waiting, and checking whether a targeted intervention improves flow.
How it connects
Connects activity time to lead time, cycle time, activity ratio, value stream mapping, CI, and review queues.

Also explained in

Compare how 6 books explain CPU time →

Related concepts

This explainer was generated by Manning's knowledge graph from the text of Build High Value Software Systems. The section links point to the parts of the book it draws on.