A critical path activity has zero scheduling slack: its earliest and latest start or finish times match, so any delay extends the project timeline. Slack equals latest start minus earliest start, or latest finish minus earliest finish. section 13.3.3
Classify activities through critical path method analysis:
- Use a forward pass to determine earliest start and finish times. section 13.3.3
- Use a backward pass to determine latest start and finish times. section 13.3.3
- Treat zero-slack activities as critical and activities with positive slack as noncritical. section 13.3.3
- For completion-risk analysis, sum the variances of critical path activities when activity times are statistically independent. section 13.4
Automated reporting tool project
Activities A–E, G, and J–L have zero slack and therefore lie on the critical path. Activity F has five weeks of slack, H has five, and I has nine, allowing those activities to move without changing the overall timeline. section 13.3.3
Table 13.3 CPM results for the automated reporting tool project. Activities in any project have slack or no slack, which is derived by subtracting the earliest start from the latest start or, alternatively, by subtracting the earliest finish from the latest finish (it doesn’t matter). Activities with no slack are on the critical path, whereas activities with slack are not.
|
Activity
|
Earliest start (ES)
|
Earliest finish (EF)
|
Latest start (LS)
|
Latest finish (LF)
|
Slack (LS – ES)
|
Critical path?
|
|---|---|---|---|---|---|---|
|
A
|
0
|
3
|
0
|
3
|
0
|
Yes
|
|
B
|
3
|
5
|
3
|
5
|
0
|
Yes
|
|
C
|
5
|
8
|
5
|
8
|
0
|
Yes
|
|
D
|
8
|
13
|
8
|
13
|
0
|
Yes
|
|
E
|
13
|
16
|
13
|
16
|
0
|
Yes
|
|
F
|
8
|
12
|
13
|
17
|
5
|
No
|
|
G
|
16
|
20
|
16
|
20
|
0
|
Yes
|
|
H
|
12
|
15
|
17
|
20
|
5
|
No
|
|
I
|
12
|
15
|
21
|
24
|
9
|
No
|
|
J
|
20
|
24
|
20
|
24
|
0
|
Yes
|
|
K
|
24
|
27
|
24
|
27
|
0
|
Yes
|
|
L
|
27
|
29
|
27
|
29
|
0
|
Yes
|
Compare earliest and latest schedule times, slack, and critical-path classification for every project activity. section 13.3.3