Earliest finish time

As explained in Statistics Every Programmer Needs

An earliest finish time is the earliest point at which a project activity can be completed based on its earliest start and expected duration.

Earliest finish time (EF) is the earliest point at which an activity can be completed. Calculate it by adding expected activity duration to earliest start time: EF = ES + duration. section 13.3 section 13.3.1

Use earliest finish times during a forward pass through a dependency network:

  • Start an activity when its prerequisites finish; when multiple predecessors exist, use the latest predecessor earliest finish time as the activity’s earliest start. section 13.3.1
  • Add the activity’s expected duration to its earliest start time to obtain its earliest finish time. section 13.3.1
  • Use the resulting finish times to determine the project timeline and support critical-path identification. section 13.3

Automated reporting tool project

Activity A starts at week 0 and lasts 3 weeks, so its earliest finish is week 3. Activity B then starts at week 3, lasts 2 weeks, and finishes at week 5. Extending the forward pass across the network produces a 29-week project timeline. section 13.3.1

Figure 13.2 A visual representation of the automated reporting tool project plan, where each activity is represented by its unique identifier. Lines and arrows between activities represent dependencies. The sequence of digits immediately beneath each activity represents, in order, the activity’s earliest start time, expected duration, and earliest finish time. The earliest times are derived by using a forward pass through the network. Based on this analysis, the project timeline is 29 weeks, which is the length of the longest path in the network.
figure

Trace each activity’s earliest start, duration, and earliest finish across the dependency network. section 13.3.1

How Statistics Every Programmer Needs covers it

How deep it goes
Explains the formula, predecessor rule, forward-pass procedure, and project-timeline interpretation.
Examples
Uses Activities A and B and a dependency network whose forward pass yields a 29-week project timeline.
What it assumes
Assumes activity dependencies and expected durations, while defining earliest starts and finishes from those inputs.
What you can do after
Apply it via the critical path method to calculate activity finish times and estimate the project’s earliest completion.
How it connects
Connects earliest start time, critical path method, forward pass, latest finish time, and slack.