A deterministic model uses fixed inputs to produce a single-point estimate. Unlike Monte Carlo simulation, it does not represent a distribution of outcomes caused by input variability. section 9.1
This distinction matters when uncertainty is significant: a single prediction can conceal the range of possible outcomes and tail risks. Monte Carlo simulation uses random sampling to explore that variability. section 9.1
Project duration
A deterministic estimate might predict a project will take exactly 20 days. A Monte Carlo simulation could instead estimate a 70% chance of finishing within 22 days and a 10% chance of exceeding 25 days. section 9.1
Call-center staffing
Daily absenteeism and call volume vary, so a deterministic staffing estimate can miss service-level risks and idle-worker costs. Monte Carlo scenarios help explore the trade-off. section 9.3